Micron AI Production Planning Copilot
AI-Assisted Planning, Exception Detection & Completion-Date Forecasting
Read-Only Monitor G5 IntegrationPilot Mode
Control TowerMO-31468QC & Rework Exception
MO-31468 · PN-AE-22014 · CNC-03

QC & Rework Exception

Ensure quality events immediately influence the production forecast.

Original Planned Completion
16 Aug
Customer Required
18 Aug
Current Forecast
20 Aug
Projected Delay
+2 Days
Risk
AT RISK
Quality event

QC Exception Details

Detected
12 Aug, 10:24 AM
Operation
OP40 — CNC Milling
Affected Qty
4
Defect
Dimensional Non-Conformance
QC Inspector
QC User A
Disposition
REWORK
Evidence

Supporting Inspection Image

Close-up dimensional inspection of a machined aerospace bracket
OP40 bore diameter — 4 units outside tolerance band
Disposition workflow

Rework Status Flow

QC Detected
Awaiting Disposition
Rework Assigned
Rework in Progress
Awaiting Reinspection
Accepted & Closed
Planning impact · 8–24 Aug

Rework Planning Impact — Original vs Rework-Adjusted Plan

+2 Days vs Customer Required
91113151719212324
Aug
Original CNC Sequence
OP10–OP40
Original QC Inspection
Original Completion
16 Aug
Rework Execution
13 → 15 Aug
QC Reinspection
Updated MO Completion
20 Aug
Original planRevised planDelay driverCustomer Required Date18 AugUpdated MO Completion20 Aug
AI recommendation

Recover the rework within the QC window

Priority: High
  1. 1Begin rework by 13 Aug
  2. 2Complete rework by 15 Aug
  3. 3Prioritise QC reinspection ahead of queue
  4. 4Review customer commitment if rework misses target