Manufacturing OrderCRITICAL
MO-35540
PN-AE-48721Material ETA change detected · delivery impact requires planner review
Critical Delivery Risk — +7 Working DaysCustomer: Aerostructures Programme B · Work Centre CNC-05
Customer Required Date
18 Aug
Current ERP Planned Completion
18 Aug
Copilot Projected Completion
25 Aug
Projected Delay
+7 Working Days
Planning timeline · 1–30 Aug
MO Planning Gantt — Original vs Copilot Revised Plan
135791113151719212325272930
Aug
Material Delivery
ETA 2 Aug
Supplier slip → 9 Aug
Receiving & Inspection
3 wd
CNC Operation 10
CNC-05
CNC Operation 20
CNC-05
Special Process
Heat treat
QC Inspection
Final Completion
Original planRevised planDelay driverCustomer Required Date — 18 AugCopilot Projected Completion — 25 Aug
Exception detected
Material ETA Changed
Original Supplier ETA2 Aug
Latest Supplier ETA9 Aug
Receiving / Inspection Allowance3 Working Days
Earliest Material Ready12 Aug
Current MO Planned Start5 Aug
Recommended MO Start12 Aug
Projected Completion25 Aug
Causal analysis
Why is this MO at risk?
Supplier ETA Delay
Material Not Ready
MO Cannot Start
CNC Sequence Impacted
Completion Pushed
Customer Delivery Risk
The supplier ETA moved from 2 Aug to 9 Aug. With a 3 working-day receiving and inspection allowance, the earliest material-ready date becomes 12 Aug. Because CNC-05 operations are sequential and no alternate routing exists in the current MPS, the entire downstream sequence shifts by seven working days, pushing final completion beyond the customer required date.
AI planning recommendation
Reschedule MO planned start from 5 Aug to 12 Aug
Recommended Start
12 Aug
Projected Completion
25 Aug
Delivery Impact
7 working days late
Recommended recovery actions
- 1Escalate purchase order with SCM
- 2Review expedited supplier delivery
- 3Load another material-ready MO into CNC-05
- 4Review customer commitment
- 5Continue monitoring supplier ETA changes
Planner decision
Approval records the planner decision only. Monitor G5 remains read-only during pilot — the date change is applied manually and verified automatically.
Data confidence
Data Sources & Lineage
Monitor G5Read-only
MOBOMMaterialPOSupplier ETARoutingWork CentreProduction Dates
MPSPlanning input
PriorityPlanner Remarks
CopilotDerived
Exception LogicWorking-Day CalculationDelivery-Risk Assessment
Traceability
Audit Trail
- 09:15Supplier ETA change detected
- 09:16Affected MO identified
- 09:17Completion forecast recalculated
- 09:17Risk changed: On Track → Critical
- 09:18Planner alerted
- 09:25Planner reviewed recommendation